Stony Creek Pedestrian Trail Under SR 37

Stony Creek Trail

PROJECT: Stony Creek Pedestrian Trail Under State Road 37

TIMELINE: Utility work began in 2022. The construction team mobilized prior to Thanksgiving and will begin work after the holiday. Construction will continue in 2023 and the trail is expected to be open by early summer 2023.

PROJECT GOALS: Increased pedestrian safety and trail connectivity.

OWNER: City of Noblesville

ENGINEER: CHA Consulting

CONTRACTOR: Oclo

SCOPE: Adding a 10-foot wide trail under State Road 37 connecting existing trails and removing a vehicular barrier to pedestrians. 

MILEAGE: 0.2 miles

ESTIMATED COST: $1.4 million

  • The city received a $765,000 federal grant for this project.

COUNCIL DISTRICT: 5 (Greg O'Connor)

Road